Metalworking: lead time halved
Sheet metal work, 45 employees1Background
Customers were calling more and more often to ask where their order was. Planning ran on Excel and there were half-finished orders all over the floor.
2Current situation

An order took 10 working days on average. The real work took just over 6 hours. At powder coating the work sat waiting for 3 days.
3Goal
Lead time under 6 days, without extra people or overtime.
4Causes
- Orders were sawn in large batches, so everything waited for the last sheet
- Coating only went out once a week
- Nobody could see which order came first
5Measures
- Sawing in small batches per order
- Two fixed collection times a week at the coater
- One planning board with the order for everyone
- Fixed place for every semi-finished part, with yellow floor marking
6Result
7Embedding
A fifteen-minute daily start at the planning board every morning at 07:30. The team leader tracks the lead time every week.